THE MASSACHUSETTS PORT AUTHORITY has selected a developer to build a mixed-use project to include 595 rental housing units at the Anderson Regional Transportation Center in Woburn.

Massport’s board unanimously approved Cabot, Cabot & Forbes as the developer of the project spanning six acres of the 26-acre transportation facility. The developer’s proposal includes 10,000 square feet of ground-floor retail space, 595 parking spaces and affordable housing options, Andrew Hargens, Massport’s chief development officer, said during Thursday’s board meeting. The development will include five residential floors over a two-level podium that houses parking as well as amenities and retail space, he said.

The transportation center is home to Massport’s Woburn Logan Express, which offers bus service to and from Logan International Airport. It also sits along both the Lowell Line of the MBTA Commuter Rail and Amtrak’s Downeaster line.

CC&F was the only developer to respond to an RFP seeking mixed-use development on the site, Hargens said. He added that the agency was looking for proposals that “capitalize on the transit-oriented development potential of the property.”

The transit center sits within the 245-acre Industri-Plex Superfund site that was once home to a chemical and glue manufacturing facility, according to the U.S. Environmental Protection Agency. Hargens said it was “paramount” the chosen developer had experience and ability to work with the EPA and address protection measures for the site. He said that CC&F is “extremely experienced” in the local market, has worked with Woburn officials and on projects of a similar scale within the same Superfund site.

MassDOT and the MBTA co-own the transportation center with Massport. MassDOT and the T are expected to approve CC&F as the site’s developer soon, Massport said in a press release. After that, the agencies and developer will work on finalizing a term sheet and development agreement, Hargens said.

Massport said the project is expected to be finished in 2031.